Each townhome is built in about 12–18 months under the construction payment programme; the show townhome is finished
Developer's programme / 01
Each townhome is built in about 12–18 months under the construction payment programme; the show townhome is finished
- Show townhome
- Finished and photographed
- Build time per villa
- 12–18 months from commencement
- Registration
- About 180 days after completion and full payment
- Warranty
- 1 year building structure
The villas are sold under the developer's construction payment plan, so each payment is triggered by a milestone of the townhome: contract, concrete structure, roof and brickwork, services and plastering, completion. The developer's briefing puts the build of an individual townhome at roughly 12–18 months and registers the land lease and the building about 180 days after completion and full payment.
Current photographs of any villa are sent on request together with its completion status; this page carries the programme and the payment stage each milestone triggers.
Programme / 02
The works, and the payment stage each one triggers
- 01Contract signed — 20% of the price (the reservation fee counts towards it)
- 02Concrete structure substantially complete — 25% milestone, 20% (or 10% on the deferred plan)
- 03Roof, brickwork and rendering complete — 50% milestone, 20% (or 10%)
- 04Electrical conduits, pipework and plastering complete — 75% milestone, 20% (or 10%)
- 05Completion of construction, about 12–18 months after start — final 20%, or the 50% balance financed over 1, 3 or 5 years
- 06Registration at the Land Department about 180 days after full payment; one-year building structure warranty from completion

The status of your villa
Name the villa; we send the developer's latest photographs and the written handover timing.
Independent advice from Invest Phuket · we reply within 15 minutes in working hours.
Discuss Banyan Tree Beach Residences Nammu with Lina
Name the plot, budget and timing. Lina answers with the current availability, the price and the terms in writing.